Keller Avenue Project Updates

Construction Updates

Keller Avenue Construction Project Update for May 5, 2021

 The crews are finishing up storm sewer at the Elm Street intersection.


Sanitary sewer is in from Center Street to Bittersweet Homestead.

 

Center Street intersection:

               They are extending the water main in each direction.

               The sanitary sewer is extending to the east because there is a bad manhole on Center Street.

               Lastly, storm water drains will be installed.

 

Crews are on schedule to finish all underground piping by the end of the week. As always, this is tentative barring any surprises.

 

They are continuing to pull sidewalks on the south end past Soo Line Park.

 

Concrete is still on schedule for Friday.

 

The crews have a very ambitious schedule and are doing a great job!

Facebook Twitter Email

Other News in Homepage News and Notices

Diggers Hotline

Digger's Hotline

Posted on: April 15, 2021
Amery Police Department Logo 55

No Parking Signs

Posted on: March 29, 2021
Summer Thursdays

Summer Thursday's Schedule

Posted on: November 16, 2020
Aerial view of the brick building of City Hall

City Hall Face Coverings

Posted on: November 13, 2020
Polk County Recycling Info

Polk County Recycling Center Information

Posted on: January 11, 2021